ABOUT THE PROJECT

Jurassic Solar+ began development in early 2021. The project includes approximately 1,200 acres of land located approximately 2.7 km west of the Hamlet of Iddesleigh, Alberta, in Special Area No. 2 and Cypress County. The project is located in Townships 20 and 21, Range 10, West of the Fourth Meridian, on privately owned, cultivated land. The Project area has a strong solar resource, characteristic of Alberta, and will generate clean energy over its 35+ year lifetime.  

Jurassic Solar+ is comprised of the 220 MW solar power plant project, “Jurassic Solar”, and the 80MW/160MWh battery energy storage system (“BESS”) project, “Jurassic BESS”.

The Jurassic Solar+ project will involve installing solar PV modules, inverter/transformer stations, a battery energy storage system, an electrical collection system, access paths, and the construction of a Project Substation to connect to the Alberta Interconnected Electric System (AIES). 

PROJECT LOCATION

Jurassic Solar+ Location

PRELIMINARY ANTICIPATED TIMELINE

 

Ongoing: Consultation with Rightsholders & Stakeholders 

Update to Rightsholders & Stakeholders: Q4 2024 

Letter of Enquiry Amending Application to AUC: Q4 2024 

Anticipated AUC Amendment Approval: H1 2025 

BESS Construction Commencement: H1 2025 

Solar Power Plant Construction Commencement: H2 2026 

BESS Commercial Operation Date (COD): H2 2026 

Solar Power Plant COD: H1 2028 

Note: Timeline is subject to change.